News Release

Contracts signed for ELT mirrors and sensors

Business Announcement

ESO

The Optical System of the ELT Showing the Location of the Mirrors

image: This diagram shows the novel 5-mirror optical system of ESO's Extremely Large Telescope (ELT). Before reaching the science instruments the light is first reflected from the telescope's giant concave 39-meter segmented primary mirror (M1), it then bounces off two further 4-meter-class mirrors, one convex (M2) and one concave (M3). The final two mirrors (M4 and M5) form a built-in adaptive optics system to allow extremely sharp images to be formed at the final focal plane.

Contracts for the casting of the M2 and M3 mirrors, their cells and sensors for the M1 segments were awarded at a ceremony at ESO's Garching Headquarters in January 2017. view more 

Credit: ESO

The construction of the 39-metre ELT, the largest optical/near-infrared telescope in the world, is moving forward. The giant telescope employs a complex five-mirror optical system that has never been used before and requires optical and mechanical elements that stretch modern technology to its limits.

Contracts for the manufacture of several of these challenging telescope components have just been signed by ESO's Director General, Tim de Zeeuw, and representatives of three industrial contractors in the ESO Member States.

Introducing the ceremony, Tim de Zeeuw said: "It gives me great pleasure to sign these four contracts today, each for advanced components at the heart of the ELT's revolutionary optical system. They underline how the construction of this giant telescope is moving ahead at full speed -- on target for first light in 2024. We at ESO look forward to working with SCHOTT, SENER and FAMES -- three leading industrial partners from our Member States."

The first two contracts were signed with SCHOTT by Christoph Fark, Executive Vice President. They cover the casting of the ELT's largest single mirrors -- the 4.2-metre secondary and 3.8-metre tertiary mirror -- from SCHOTT's low-expansion ceramic material Zerodur© [1].

Hanging upside-down at the top of the telescope structure, high above the 39-metre primary mirror, the secondary mirror will be largest ever employed on a telescope and the largest convex mirror ever produced [2]. The concave tertiary mirror is also an unusual feature of the telescope [3]. The ELT secondary and tertiary mirrors will rival in size the primary mirrors of many modern-day research telescopes and weigh 3.5 and 3.2 tonnes respectively [4]. The secondary mirror is to be delivered by the end of 2018 and the tertiary by July 2019.

The third contract was signed with the SENER Group by Diego Rodríguez, Space Department Director. It covers the provision of the sophisticated support cells for the ELT secondary and tertiary mirrors and the associated complex active optics systems that will ensure these massive, but flexible, mirrors retain their correct shapes and are correctly positioned within the telescope. Great precision is needed if the telescope is to deliver optimum image quality [5].

The fourth contract was signed by Didier Rozière, Managing Director (FAMES, Fogale), and Martin Sellen, Managing Director (FAMES, Micro-Epsilon), on behalf of the FAMES consortium, which is composed of Fogale and Micro-Epsilon. The contract covers the fabrication of a total of 4608 edge sensors for the 798 hexagonal segments of the ELT's primary mirror [6].

These sensors are the most accurate ever used in a telescope and can measure relative positions to an accuracy of a few nanometres. They form a fundamental part of the very complex system that will continuously sense the locations of the ELT primary mirror segments relative to their neighbours and allow the segments to work together to form a perfect imaging system. It is a huge challenge not only to make sensors with the required precision, but also to produce them quickly enough for thousands to be delivered to the necessarily short timescales.

The signing ceremony was also attended by other senior representatives of the companies involved and ESO. It was an excellent opportunity for representatives of the contractors producing many of the giant telescope's optical and mechanical components to get to know each other informally as they begin to help create the world's biggest eye on the sky.

###

Notes

[1] Zerodur was originally developed for astronomical telescopes in the late 1960s. It has almost no thermal expansion, which means that even in the case of large temperature fluctuations, the material does not expand. Chemically, the material is very resistant and can be polished to a high standard of finish. The actual reflective layer, made of aluminum or silver, is usually vaporised onto the extremely smooth surface shortly before the telescope is put into operation. Many well-known telescopes with Zerodur mirrors have been operating reliably for decades. They include, for example, ESO's Very Large Telescope in Chile.

[2] As it is a highly convex, aspherical mirror, fabrication of the secondary is a considerable challenge and the result will be a truly remarkable example of precision optical engineering. As with many elements of the ELT it will be a genuine first in this area of technology. The total weight of the secondary mirror and its support system is 12 tonnes -- and since it hangs over the primary great care must be taken to prevent the mirror from falling!

[3] Most current large telescopes, including the VLT and the NASA/ESA Hubble Space Telescope, use just two curved mirrors to form an image. In these cases a tertiary mirror is sometimes introduced to divert the light to a convenient focus -- that mirror is typically small and flat. However, in the ELT the tertiary also has a curved surface, the use of three mirrors delivering a better final image quality over a larger field of view than would be possible with a two-mirror design.

[4] The contract for the polishing of the secondary mirror has already been awarded.

[5] The M2 and M3 cells are complex mechanisms more than 6.5 metres wide and weighing close to 12 tonnes including the mirrors themselves. They provide alignment and tracking capabilities with a high precision hexapod with an absolute accuracy of tens of micrometres. The cells also compensate for mirror surface deformations in the order of tens of nanometres by means of an innovative solution using warping harnesses and lateral supports.

[6] At this time 3288 have been firmly ordered (for the ELT Phase 1) and an additional 1320 will be included in the ELT Phase 2, making 4608 in total.

More information

ESO is the foremost intergovernmental astronomy organisation in Europe and the world's most productive ground-based astronomical observatory by far. It is supported by 16 countries: Austria, Belgium, Brazil, the Czech Republic, Denmark, France, Finland, Germany, Italy, the Netherlands, Poland, Portugal, Spain, Sweden, Switzerland and the United Kingdom, along with the host state of Chile. ESO carries out an ambitious programme focused on the design, construction and operation of powerful ground-based observing facilities enabling astronomers to make important scientific discoveries. ESO also plays a leading role in promoting and organising cooperation in astronomical research. ESO operates three unique world-class observing sites in Chile: La Silla, Paranal and Chajnantor. At Paranal, ESO operates the Very Large Telescope, the world's most advanced visible-light astronomical observatory and two survey telescopes. VISTA works in the infrared and is the world's largest survey telescope and the VLT Survey Telescope is the largest telescope designed to exclusively survey the skies in visible light. ESO is a major partner in ALMA, the largest astronomical project in existence. And on Cerro Armazones, close to Paranal, ESO is building the 39-metre Extremely Large Telescope, the ELT, which will become "the world's biggest eye on the sky".

Links

* Further information about the ELT - http://eso.org/e-elt

* Further information on SCHOTT - http://schott.de

* Further information on the SENER group - http://www.aerospace.sener

* Further information on Fogale - http://www.fogale.fr/ and Micro-Epsilon - http://www.micro-epsilon.com/?sLang=en (the FAMES consortium)

Contacts

Richard Hook
ESO Public Information Officer
Garching bei München, Germany
Tel: +49 89 3200 6655
Cell: +49 151 1537 3591
Email: rhook@eso.org


Disclaimer: AAAS and EurekAlert! are not responsible for the accuracy of news releases posted to EurekAlert! by contributing institutions or for the use of any information through the EurekAlert system.