News Release

Successful design review: ATV gets go-ahead

Peer-Reviewed Publication

European Space Agency

Over the past three and a half months, around 40 engineers from the RSC Energia, 25 from NASA and over 50 from ESA, CNES and Arianespace conducted a full review of the ATV programme through its extensive documentation (presented in electronic format) and did not find anything wrong which would require a change in the design. Seven panels, each consisting of 15 to 20 people, were charged with thoroughly reviewing the various aspects of the programme, such as avionics, systems, software, structure, thermics, as well as quality and operations. Teams from ESA and prime contractor EADS-LV answered their questions and clarification requests.

"The successful completion of the Critical Design Review for the ATV is an extremely important milestone for Europe's contribution to the ISS. The way is now free for the assembly of the first ATV, Jules Verne, and its maiden flight planned for September 2004. Together with the Columbus laboratory, ATV is a key European element," said Jörg Feustel-Büechl, ESA's Director of Human Spaceflight.

The purpose of the review was to assess and certify that the ATV design and operations concept meets the requirements for performance, reliability, and safety. The ATV project manager, Robert Lainé, compared the CDR process to sieving through the complete programme to find possible bugs. "The members of these external panels raised some good questions," said Lainé. "Such as asking how the ATV could depart if the ISS was in a critical attitude, or if the ATV should have an extra software backup for re-entry. These remarks are very beneficial, because they help us to think about solutions to possible problems before flying".

In 2000, the Preliminary Design Review (PDR) had to be extended by six months to rethink the overall concept of navigation and guidance, rewrite some specifications and make a few hardware changes. For example, another set of optical sensors (Videometre) was added for rendezvous and docking, and a set of Variable Conductance Heat Pipes (VCHP) was added to cope with large changes in power dissipation in the avionics bay of the spacecraft during orbit.

The successful conclusion of the review is important for the ATV programme since 90% of the flight hardware is already built and the final assembly process started. Any design change would have significantly impacted the scheduled launch of Jules Verne set for September 2004.

"The programme is ready to proceed to the next step, yet there is significant work to be done to complete ATV. But we didn't see any design issues that would be a cause to stop or pause. The ATV is on a tight schedule with many challenges ahead. It's scheduled to fly in September 2004, but the team is well prepared and the design is ready to go into final build", said Bill Gerstenmaier, the International Space Station Programme Manager at NASA who came to ESA's European Space and Technology Centre (ESTEC) in Noordwijk, The Netherlands, June 4 to attend the final CDR board meeting.

"The success of CDR was a joint effort of European industry and the ESA management team with important involvement of our Russian partners Rosaviakosmos and RSC Energia and full support from the NASA programme team. All contributors should be congratulated for their commitment and encouraged to complete the development of this highly complex spacecraft," said Feustel-Büechl.

###


Disclaimer: AAAS and EurekAlert! are not responsible for the accuracy of news releases posted to EurekAlert! by contributing institutions or for the use of any information through the EurekAlert system.